SANDSTROM, Justice.
[¶ 1] JB Mineral Services, LLC ("JB"), appeals from a summary judgment declaring an oil and gas lease terminated and awarding statutory damages, costs, and attorney fees to Dahn P. Beaudoin and J. Willard Beaudoin, as trustees of the William Beaudoin Irrevocable Mineral Trust ("Beaudoins"). We affirm, concluding the district court did not err in concluding JB failed to timely pay or tender the sum required to continue the lease and the lease automatically terminated by its express terms.
[¶ 2] JB is a Montana limited liability company that sought to lease certain oil and gas interests owned by Beaudoins in Stark County. In July 2009, JB sent to Beaudoins an oil and gas lease, a supplemental agreement, and a document JB alleges was a 120-day sight draft
[¶ 3] On January 6, 2010, JB sent a revised lease and a 25-day sight draft to Beaudoins, reflecting JB's claim that Beaudoins owned 3.68 fewer mineral acres than covered in the original lease. The revised lease would also have extended the term of the lease approximately six months longer than the July 2009 lease. Beaudoins never executed or agreed to the revised lease and did not present the second sight draft, which was for less than the original sight draft, for payment.
[¶ 4] Beaudoins claim that the "termination date" under the supplemental agreement was January 12, 2010, which was 120 business days after they signed the lease and supplemental agreement on July 20, 2009. On January 19, 2010, Beaudoins' counsel faxed a letter to JB advising that Beaudoins considered the lease terminated and invalid and that any subsequent attempt to pay the July 2009 sight draft would be rejected. JB's counsel replied by faxed letter the same day, advising that JB's position was that it had until January 20, 2010, to pay the supplemental bonus payment by funding the July 2009 sight draft. Beaudoins' counsel responded by faxed letter dated January 20, 2010, reiterating that the lease had already terminated and was invalid. JB never authorized payment of the July 2009 sight draft, but recorded the original July 2009 lease
[¶ 5] Beaudoins sued JB to have the lease declared invalid and for statutory damages, costs, and attorney fees under N.D.C.C. § 47-16-37. Beaudoins moved for summary judgment. The district court granted summary judgment, concluding the parties' agreement unambiguously provided that the lease terminated on January 12, 2010, 120 business days after the notarized signatures by the Beaudoins, when JB failed to make the required bonus payment by that date. The court awarded Beaudoins statutory damages, costs, and attorney fees.
[¶ 6] The district court had jurisdiction under N.D. Const. art. VI, § 8, and N.D.C.C. §§ 27-05-06 and 47-16-37. JB's appeal was timely under N.D.R.App.P. 4(a). This Court has jurisdiction under N.D. Const. art. VI, §§ 2 and 6, and N.D.C.C. § 28-27-01.
[¶ 7] We have outlined the standards governing summary judgment under N.D.R.Civ.P. 56:
Lucas v. Riverside Park Condos. Unit Owners Ass'n, 2009 ND 217, ¶ 16, 776 N.W.2d 801 (quoting Barbie v. Minko Constr., Inc., 2009 ND 99, ¶ 5, 766 N.W.2d 458). If the moving party meets its initial burden of showing the absence of a genuine issue of material fact, the party opposing the motion may not rest on mere allegations or denials in the pleadings but must present competent admissible evidence to show the existence of a genuine issue of material fact. E.g., Barbie, at ¶ 6. Mere speculation is not enough to defeat a motion for summary judgment, and when no pertinent evidence on an essential element is presented to the district court in resistance to the motion for summary judgment, it is presumed no such evidence exists. Id.
[¶ 8] JB first contends the July 2009 lease is valid because a royalty clause alone is sufficient consideration for an oil and gas lease under Irish Oil & Gas, Inc. v. Riemer, 2011 ND 22, 794 N.W.2d 715.
[¶ 9] In Irish Oil, the lessors argued the lessee's failure to timely pay bonus payments constituted a total failure of consideration for their oil and gas leases. Irish Oil, 2011 ND 22, ¶ 21, 794 N.W.2d 715. A majority of this Court held that because the leases also contained royalty clauses, the question whether failure to pay the bonus payments constituted a total failure of consideration or a partial failure
[¶ 10] Beaudoins have not argued that the lease in this case failed for lack of consideration. Rather, Beaudoins contend the lease terminated by its own terms through operation of an "unless" clause. The relevant provisions in the parties' supplemental agreement state:
[¶ 11] These provisions of the parties' agreement constitute an "unless" clause. An "unless" clause provides that the lease shall terminate unless the lessee does some specific act, such as commencing a well or making specified payments. 3 Howard R. Williams and Charles J. Meyers, Oil and Gas Law § 606 (2010). This Court has explained the application of an "unless" clause:
Serhienko v. Kiker, 392 N.W.2d 808, 811-12 (N.D.1986); see also Borth v. Gulf Oil Exploration & Prod. Co., 313 N.W.2d 706, 709 (N.D.1981); Norman Jessen & Assocs., Inc. v. Amoco Prod. Co., 305 N.W.2d 648, 650 (N.D.1981).
[¶ 12] Beaudoins do not contend the lease in this case failed for lack of consideration, but rather argue it automatically terminated by its express terms under the "unless" clause when JB failed to timely tender payment. The leases in Irish Oil did not contain "unless" clauses, and the holding in that case was based solely upon the lessors' contention that there had been a total failure of consideration which invalidated the leases. The holding in Irish Oil does not apply to this case.
[¶ 13] JB contends the district court erred in holding the lease had terminated by its express terms when JB failed to make the supplemental bonus payment by January 12, 2010, the termination date in the contract. JB summarized its argument in its brief on appeal:
[¶ 14] Under the terms of the supplemental agreement, the lease terminated 120 days after "notarized signature" unless JB, "on or before said Termination Date, shall pay or tender to" Beaudoins "the sum of Forty Five Dollars ($45.00) per net mineral acre." The agreement further provided: "The payment or tender of said sum may be made by cash, check, or draft, mailed or delivered to" Beaudoins "on or before said Termination Date." There is no dispute that Beaudoins signed the lease and supplemental agreement on July 20, 2009, and the 120 business days expired on January 12, 2010. The district court concluded that the supplemental agreement unambiguously required payment of the bonus by January 12 and that the lease terminated by its own terms when payment was not received by that date.
[¶ 15] JB contends, however, that the agreement did not require payment actually be made by January 12, but merely required that payment be tendered, by cash, check, or draft, by that date. Thus, JB argues tender of the $165,600 sight draft in July 2009 constituted tender of a draft for the amount of the supplemental bonus payment within the contractual period and continued the lease, even if payment of the draft was not due until after the termination date. JB further argues that it had until January 20, 2010, to authorize payment of and fund the July 2009 sight draft.
[¶ 16] The language of the parties' supplemental agreement is clear and unambiguous. The first sentence of subsection 1 of the supplemental agreement provides that the lease shall terminate 120 business days from date of notarized signature unless JB "shall pay or tender" to Beaudoins "the sum of Forty Five Dollars ($45.00) per net mineral acre" on or before that termination date. Similarly, the second sentence in subsection 2 states that "[i]f such sum is not timely paid or tendered, then said lease shall terminate."
[¶ 17] JB was clearly required to pay or tender the sum of $45.00 per mineral acre for the minerals covered under the lease by January 12, the termination date specified in the agreement. Payment or tender of the sum requires more than tender of a draft which by its terms was not payable until a future date after January 12 and which was admittedly not funded by January 12. Carried to its logical extreme, JB's argument that it could satisfy the requirements of the agreement merely by tendering a draft which was payable at some future date by the January 12 deadline would allow a lessee to submit a draft which was not payable until weeks, months, or even years after the termination date. If all that is required is tender of a draft, without regard to the date the draft becomes payable or is funded, the lessee would be allowed to effectively extend the termination date indefinitely.
[¶ 18] JB relies upon the language in the parties' agreement providing that "payment or tender of said sum may be made by cash, check, or draft, mailed or
[¶ 19] Although it may appear harsh to enforce the automatic termination provision in the agreement against JB under these circumstances, we again note that the provisions in the supplemental agreement constitute an "unless" clause. This Court has recognized that the "unless" clause was developed for the benefit of the lessee, and is strictly construed against the lessee even though harsh results may occur:
Norman Jessen & Assocs., 305 N.W.2d at 651. The burden of preventing a lease with an "unless" clause from terminating lies upon the lessee, and if the payments required by the lease are deficient in either the time or the amount of payment, the lease terminates automatically. Borth, 313 N.W.2d at 709. Professors Williams and Meyers further explain:
3 Williams & Meyers, supra, § 606.2 (footnote omitted). Thus, courts have been "substantially unanimous" in holding that the lease terminates automatically if the lessee fails to pay or tender the required payment on or before the due date, including when the payment was late by as little as one day, or was tendered to the wrong bank or the wrong party, or was misaddressed in mailing, or was late because of mistake as to the proper due date. Id.
[¶ 20] The result we reach in this case does not conflict with the holding in Nygaard
[¶ 21] Nygaard is distinguishable from this case on several key points. The lessor in Nygaard was challenging only the form of payment, not the timeliness of the payment by sight draft. This Court rejected the claim that payment could be made only in cash, noting that the lessor had not contemporaneously objected to the form of payment and that the parties' agreement did not specify payment could only be in cash. Id. In Nygaard, the five-day sight draft was tendered 24 days before payment was due, providing ample opportunity for the lessor to present it for payment and effectively convert it to cash prior to the January 4, 1998, deadline. In this case, however, JB relies upon the use of the sight draft to attempt to extend the payment date beyond the termination date set in the parties' agreement. Beaudoins do not allege that JB could not make the payment by a sight draft, but contend that any such draft had to be payable and funded by the termination date set in the agreement. The issue in this case, unlike Nygaard, is timeliness of the payment, not its form. We also note that Nygaard involved an extension to a lease, not an "unless" clause, which requires strict construction against the lessee. See, e.g., Norman Jessen & Assocs., 305 N.W.2d at 651; 3 Williams & Meyers, supra, § 606.2.
[¶ 22] Applying the rule of strict construction of an "unless" clause to the unambiguous language of the parties' supplemental agreement, we conclude the district court did not err in concluding that JB failed to timely pay or tender the required sum under the parties' agreement and the lease automatically terminated on January 12, 2010.
[¶ 23] We have considered the remaining issues and arguments raised by the parties and find them to be either unnecessary to our decision or without merit. The summary judgment is affirmed.
[¶ 24] GERALD W. VANDE WALLE, C.J., DANIEL J. CROTHERS, MARY MUEHLEN MARING, and CAROL RONNING KAPSNER, JJ., concur.